Campbell Strawbale House Cost Breakdown

Square Feet: 1688 exterior, 1344 interior
Load-bearing structure
Earthen plaster exterior, gypsum plaster interior
House Construction Costs ONLY- does not include figures for land purchase, financing, studio construction, some tools, and travel trailer.


Back to Homestead Page


Architectural Plans $1680.00 Drafting of "to code" house plans by professional draftsperson
Utilities Hookup $499.59 Electric power materials­ 200Amp service box & meter, ground rods, etc.
Water pipe & fittings to bring running water to building site from well.
Septic System $1,500.00 Septic tank and installation by professional (not me).
Concrete Foundation $7,642.00 Cement slab­ subcontractor labor & materials fees for preparing housesite with rebar & wire mesh, and pouring and smoothing cement slab.
Sidewalks/Driveways $174.38 Concrete & other materials for west side utility area "floor."
Waterproofing $18.42 Henry 107 for above the footer, under the strawbale walls (required by local Tucson/Pima County code)
Strawbales $1,597.00 Total of 464 strawbales (delivered) for exterior walls of house and studio.
Fireplace/Wood burning stove $1,253.80 Chimney parts and new freestanding woodburning stove.
Framing Labor $415.00 Labor fees of experienced and learning helpers for trusses and roof sheathing.
Rough Lumber/Materials $4,771.15 Miscellaneous line item of lumber, rebar, allthread, screws, nails, etc. that includes materials from window & door bucks built in March, 2000 through shelving built in November, 2001.
Trusses $1,985.28 Wooden trusses (manufactured by local company, Lumberyards Inc.), nails and simpson ties for roof trusses.
Sheathing $1,611.63 OSB (particle board), nails and clips for roof sheathing.
Plumbing $4,772.42 Supply lines, intermediate plumbing, and fixtures.
Rough-in plumbing was done by subcontractor (Desert Women Plumbing) for $2,600.00, included in total plumbing cost figure above.
Electrical $3,490.87 Wire, outlet and switch boxes, receptacles and switches, conduit, fans, lights, subpanel, breakers, etc.
Insulation $1,577 Materials and installation by Gale Insulation, local company (ceiling, R-32, and walls, R-11).
Plaster $5,885.44 Earthen plaster materials and some labor on exterior (done by ourselves and volunteers, with some help by hired hands). Gypsum plaster materials and labor for interior done by professional crew.
Heating, Venting and Cooling $1,525.10 Materials for radiant floor heating system, evaporative cooler, and cooler venting and registers.
Gutters $525 Materials and labor for professional gutter company.
Interior Doors & Trim $1,533.87 Materials for wood doors, frames, and hardware
Drywall $2,716.18 Ceilings and walls materials and labor for outside crew to hang, tape and texture. Received coving material for free.
Windows & Patio Doors $3,351.59 Windows and patio (French) doors, installed by ourselves.
Painting $675.59 Paints, brushes, etc., applied by ourselves.
Roofing $2,839.73 Beautiful green BHP metal roof, roofing felt & fasteners, caulking, etc.
Cabinets $3,551.11 Kitchen cabinets, shelving and hardware, installed by myself.
Countertops $1,000.00 Formica countertop material and installation by professional company.
Finish Carpentry $1,032.69 Trim materials and hired labor (crafstman/friend).
Flooring $1,110.83 Cement slab floor stain (acid wash) & sealer, and rugs.
Bath Accessories $213.18 Mirrors, hooks, holders, etc.
Tub/Shower Enclosures $1,900.18 Cast iron tubs, installed by myself; cultured marble material and install by professional company.
Appliances $685.87 Dishwasher, water heater; all others given to us by friends.
Landscaping $669.90 Plants, trees, weedwacker, drip system, installed by Michelle.
Consultant Fees/Supervision $537.00 Fees for master builder Jon Ruez, strawbale guru.
Fire Sprinklers $1,800.00 Cutler Fire Protection Company plan, materials, installation in house and studio.


TOTAL $65,105.37 $39/sq. ft.